INTRODUCTION: |
|
The Facilities Mater Planning meets to establish and monitor the institutions strategic Facilities Masterplan, oversee and review construction process on new facilities and to prioritize, monitor renovation projects. oversee and review construction process on new facilities and to prioritize, monitor renovation projects. |
|
|
HISTORY: |
|
|
|
The following projects listed and/or shown on the April 19, 1999 Master Plan have been completed: |
|
|
1.New Grounds Building |
|
|
|
2.New Centennial Bell Tower |
|
|
|
3.Closing of Cleveland Street, New Cleveland Plaza and new parking lot west of Cleveland Plaza. |
|
|
4.Stadium Expansion |
|
|
|
5.Willard Plaza (Phase I) |
|
|
|
6.Jungle Plaza (Gorilla Village) |
|
|
|
7.Some of the property shown on page 14 of the Master Plan has been purchased. |
|
|
The following projects listed and/or shown on the April 19, 1999 Master Plan are in design: |
|
|
1.Veteran's Memorial Amphitheater |
|
|
|
2.KSANG Readiness Center/Classroom/Rec. Center |
|
|
3.Hike/Bike Trail Extension |
|
|
|
The following major projects not shown on the April 19, 1999 Master Plan have been completed: |
|
|
1.Total remodel of Russ Hall, Horace Mann Building and Willard Hall. |
|
|
2.Major remodeling in Whitesitt Hall, McCray Hall, Kelce Building, Hughes Hall, Axe Library Basement, North Dorms Air Conditioning Phase I. |
|
|
3.New Chemical Storage Building, Message Center and "Nightsong" Statue. |
|
|
4.Building upgrades in Hartman Hall (Elevator), Weede P.E. Building (Structural Repairs, Locker Rooms, Gym Floor and Bleacher Repair). |
|
|
|
|
The following new projects are being considered for a new Master Plan up-date scheduled to be completed in 2002: |
|
|
1.New Chandler Hall Building to replace existing building.(Out for Bids) |
|
|
2.New Student Health Center. |
|
|
|
3.Adjusting the Master Plan for the two residences on Lindburg Street that have been put on the Historical Register. |
|
|
4.New Plaza and parking on south end of Stadium. |
|
|
|
5.Development of the area now occupied by the east campus apartments. |
|
|
6.Looking at future growth for the university.(Future NCAA complainant tr ack facility), (Future Research Buildings) |
|
|
|
|
|
|
PREVIOUS YEAR |
|
|
|
| May 2001 to May 2002 |
|
|
|
Russ Hall Renovation |
Close out project |
|
|
Bicknell Sports Complex Driveways/Parking project |
Close out project |
|
|
Russ Hall Tuckpointing and Restoration |
Provide project management and work for completion of Phase I. |
|
|
New Chandler Hall Building |
Provide project management and work for completion of the contract documents, bid and start construction. |
|
|
North Dorms Air Conditioning Phase II |
Provide project management and work for completion of the contract documents, bid and complete construction. This also includes the Window Replacement for Tanner Hall. |
|
|
Nation Hall - ADA Front Entry Improvements |
Provide project management and work to complete construction of project. |
|
|
Veteran's Memorial Amphitheater |
Provide project management and work for completion providing funds are raised. |
|
|
Hike/Bike Trail Extension |
Provide project management and work for completion of the contract documents, bid and start construction. |
|
|
Psychology Office Renovation in Whitesitt Hall |
Complete in-house design, bid and start construction. |
|
|
Brown Lot Overlay |
Complete in-house design, bid and start construction. |
|
|
J.H.O. Student Center Kitchen Upgrade |
Provide project management and work for completion of the contract documents, bid and start construction. |
|
|
McCray Partial Roof Replacement |
Complete in-house design, bid and complete construction. |
|
|
Shirk Hall Partial Roof Replacement |
Complete in-house design, bid and complete construction. |
|
|
Grubbs Building Doors Replacement |
Complete in-house design, bid and complete construction. |
|
|
Kelce Hall Doors Replacement |
Complete in-house design, bid and complete construction. |
|
|
Stadium Turf Replacement |
Complete in-house design, bid and complete construction. |
| |
|
East Campus Apartments Study |
Provide project management and work for completion of the study. |
| |
|
NOTE: |
|
Not all the projects listed above under the previous year have been completed.Many are under construction several are out for bid and a few are just starting design stage.Therefore, these projects will extend into next year's report. |
|
|
|
|
Capital Improvement requests |
KBOR report due April 1st. |
| |
|
Master Plan Strategic Planning Council Report |
MPSPC report due May 1st. |
|
|
|
Facilities Management Project Report |
FM report due May 15th. |
| |
|
Finalized Capital Improvement requests w/5yr plan |
KBOR report due July 1st. |
| |
|
Annual Report to the Kansas Historical Society |
KHS report due July 1st. |
| |
|
Five & 10 year plans as required by K.S.A. 76-6b03 |
KBOR report due Aug. 1st duplicates July 1st submittal. |
| |
|
Inventory of Physical Facilities & Space Utilization with a complete report done biennial |
KBOR report due Nov. 1st. |
| |
|
Rehabilitation and Repair Projects for Institutions of Higher Education |
KBOR report due Dec. 1st for allocation, at December Board meeting. |