INTRODUCTION: |
The Facilities Mater Planning meets to establish and monitor the institutions strategic Facilities Masterplan,
oversee and review construction process on new facilities and to prioritize, monitor renovation projects.
This is the first annual report of this committee's activities for the previous year that the chair is aware of.
Therefore, it may be helpful to provide a brief history of the past few years activities prior to focusing on the Facilities Planning activities for the previous year. |
|
|
HISTORY: |
|
The following is a brief overview of the Facilities Planning activities from May 1997 to May 2000. |
|
|
|
May 1997 to May 1998
|
|
|
|
|
PROJECT
|
PROJECT DESCRIPTION
|
|
|
|
|
Kansas Technology Center |
A new building was completed to house all of the technology
programs on campus, included separate contracts for
landscaping and irrigation system. |
|
|
Bowen Hall - Electrical |
The electrical system in Bowen was a complete upgrade. |
|
|
Grubbs A/C & ADA Upgrade |
A new HVAC system was installed in Grubbs and a central
chiller plant was installed to accommodate Grubbs, Yates
and Axe Library. |
|
|
Hollenbeck Memorial |
A memorial was installed in front on the west end of the
KTC for Bill Hollenbeck. |
|
|
Hughes Hall - Basement/Classrooms |
The basement area was remodel to put in a research
library and teaching classrooms |
|
|
Kelce - OIS Addition |
An additional 3,050 sq. ft. was added to the north west
side of Kelce to house an expanding OIS department.
There was also remodeling done on existing areas in
the OIS department. |
|
|
Kelce - Partial Roof Replacement |
A partial reroofing was done on Kelce |
|
|
Shirk Hall Roof |
A complete new roof system was installed on Shirk |
|
|
Shirk - University Police |
The basement of Shirk Hall was completely gutted and
remodeled especially for the University Police Department |
|
|
Student Center - Jungle Lounge |
Remodeling was done in the basement to make the new
Jungle Lounge |
|
|
Student Center - Admin Office/Window Replacement |
Remodeling was done in the basement for new offices along
with the new window replacement. |
|
|
Tanner Fire Alarm |
New fire alarm system was installed |
|
|
Whitesitt Hall - Printing Services/QP/Post Office |
The south west end on the first floor of Whitesitt Hall was
completely remodeled to house the Postoffice/Printing
Services and Quick Print as one unit. |
|
|
Whitesitt Hall - Elevator Modifications |
An elevator was installed on the south to accommodate
all floors and ADA requirements. |
|
|
Dellinger/Gibson - Fire Alarm/Electrical Upgrade |
A new fire alarm system and electrical system were
installed in Dellinger and Gibson. |
|
|
Capital Improvement requests |
KBOR report due Apirl 1st. |
|
|
Finalized Capital Improvement requests w/5yr plan |
KBOR report due July 1st. |
|
|
Five & 10 year plans as required by K.S.A. 76-6b03 |
KBOR report due Aug. 1st duplicates July 1st submittal. |
|
|
Inventory of Physical Facilities & Space Utilization |
KBOR report due Nov. 1st. |
|
|
Rehabilitation and Repair Projects for Institutions of
Higher Education |
KBOR report due Dec. 1st for allocation, at December
Board meeting. |
|
|
|
May 1998 to May 1999
|
|
|
|
Hike Bike Trail |
The new Hike/Bike trial from the parking lot from KTC to
the brown lot was done. |
|
|
Horace Mann - Abatement |
The asbestos abatement was done in Horace Mann. |
|
|
Message Center |
A new message board was installed on the corner of
Broadway and Cleveland. |
|
|
Softball Fields - Parking Lot |
The parking lot over by the Softball fields was put in. |
|
|
Softball Fields - Concession/Restroom/Bldgs |
New concession and restrooms were added to the
softball fields. |
|
|
Trout Hall - Electrical Service Replacement |
A new electrical service was put in Trout Hall. |
|
|
Weede Gym Floor |
The hardwood floor was installed in the Weede Gym. |
|
|
Weede Bleacher Repair - East/South |
Repairs were done to the east/south bleachers in order for
them to open and close properly. |
|
|
Whitesitt Hall - Suites 102,103, 105, 120 |
These suites were remodeled to accommodate the move
of Academic offices from Russ Hall. |
|
|
Willard/Mitchell Halls - Asbestos |
The asbestos abatement was done in the halls. |
|
|
Willard/Mitchell Halls - Demolition |
The demolition of Mitchell was done. |
|
|
Capital Improvement requests |
KBOR report due Apirl 1st. |
|
|
Finalized Capital Improvement requests w/5yr plan |
KBOR report due July 1st. |
|
|
Five & 10 year plans as required by K.S.A. 76-6b03 |
KBOR report due Aug. 1st duplicates July 1st submittal. |
|
|
Inventory of Physical Facilities & Space Utilization |
KBOR report due Nov. 1st. |
|
|
Rehabilitation and Repair Projects for Institutions of
Higher Education |
KBOR report due Dec. 1st for allocation, at December
Board meeting. |
|
|
|
May 1999 to May 2000
|
|
|
|
|
Campus Master Plan |
The Campus Master Plan was completed and distributed. |
|
|
Grounds Maintenance Building |
The new Grounds Maintenance Building was built north and
east of Weede. |
|
|
Horace Mann Renovation |
A complete renovation of Horace Mann was done for a
One-Stop Center for Students. |
|
|
Hughes Hall - 2nd Floor Classrooms |
The new smart classrooms were installed along with the
remodeling of the computer lab. |
|
|
Kelce Classrooms/ADA |
Kelce classrooms were brought up to ADA requirements
and remodeled for current teaching methods. |
|
|
|
|
McCray - Classrooms/ADA |
McCray hall classrooms were brought up to ADA along with
the installation of an elevator. |
|
|
Russ Hall - Roof Replacement/Temp & Perm |
A temporary roof was put on Russ till the permanent one
could be installed. |
|
|
Weede Lockers |
Remodeling of the men's/women's lockers in Weede. |
|
|
Whitesitt Hall - Fire Safety |
A new standpipe system was put in Whitesitt Hall. |
|
|
Whitesitt Hall - PII Walkway |
A walkway was built on the south side of Whitesitt Hall
from the second floor to accommodate a fire escape. |
|
|
Whitesitt Hall - PIII Classrooms/ADA |
Classroom renovation and brought up to ADA regulation. |
|
|
Willard Hall Renovation |
A complete renovation of Willard was done to make an
apartment style dorm. |
|
|
Capital Improvement requests |
KBOR report due April 1st. |
|
|
Finalized Capital Improvement requests w/5yr plan |
KBOR report due July 1st. |
|
|
Five & 10 year plans as required by K.S.A. 76-6b03 |
KBOR report due Aug. 1st duplicates July 1st submittal. |
|
|
Inventory of Physical Facilities & Space Utilization |
KBOR report due Nov. 1st. |
|
|
Rehabilitation and Repair Projects for Institutions of
Higher Education |
KBOR report due Dec. 1st for allocation, at December
Board meeting. |
|
|
PREVIOUS YEAR |
|
|
|
|
|
May 2000 to May 2001
|
|
|
|
|
Athletic Fields East of Rouse-Driveways & Parking |
New driveways and parking lots were installed over at the
Bicknell Sports Complex. |
|
|
Axe Library - Abatement |
Asbestos abatement was removed from the Axe Library
are was to be remodeled. |
|
|
Axe Library - Basement/1st Flr |
Remodeling was done in the basement to house book
stacks and the Special Collections of the library. The first
floor computer labs were enlarged. |
|
|
Bell Tower |
A new bell tower was installed between Axe Library and
the football field. |
|
|
Chandler Hall - Renovation |
Starting the roof replacement now. Will start interior
renovation late summer. |
|
|
Cleveland Plaza |
Cleveland had a cul-de-sac installed with a plaza for
students to cross safely between class changes. |
|
|
Chemical Storage Building |
A new building was built to accommodate Printing, Biology
and Chemistry since the building they were using north of
Russ Hall was demolished in the renovation of Russ. |
|
|
Gibson Dining - Sewer Replacement |
New sever lines were installed during the renovation of
Willard Hall. |
|
|
Hartman Elevator |
A new ADA elevator was installed in Hartman Hall. |
|
|
Hike/Bike Trail Expansion |
An extension from the east side of the brown lot through
the campus and also on the east side of the KTC Building. |
|
|
McPherson Parking Lot P-II |
The second parking lot south of Weede and east of
McPherson Nursing building was installed. |
|
|
Mitchell Hall - Roof Replacement |
New roof was installed on the remaining part of Mitchell. |
|
|
Russ Hall Renovation |
A complete renovation of all four floors of Russ Hall. |
|
|
Stadium Expansion/Renovation |
A new upper level was added to the east side along with
renovation of the existing area (restrooms, concession
areas etc.) with new stadium seating on both sides. |
|
|
Tanner Hall - AC & Electrical Upgrade |
AC & Electrical Upgrade will be done in Tanner. |
|
|
Weede Bleacher Repair - West |
Repairs were done to the west bleachers in order for them
to open and close properly. |
|
|
Weede P. E. Bldg - Wall Repair |
Structural repairs were done to the west side of Weede
and the dance studio. |
|
|
NOTE: |
|
Not all the projects listed above under the previous year have been completed. Many are under construction
several are out for bid and a few are just starting design stage. Therefore, these projects will extend into next
years report. |
|
|
Capital Improvement requests |
KBOR report due April 1st. |
|
|
Finalized Capital Improvement requests w/5yr plan |
KBOR report due July 1st. |
|
|
Five & 10 year plans as required by K.S.A. 76-6b03 |
KBOR report due Aug. 1st duplicates July 1st submittal. |
|
|
Inventory of Physical Facilities & Space Utilization |
KBOR report due Nov. 1st. |
|
|
Rehabilitation and Repair Projects for Institutions of
Higher Education |
KBOR report due Dec. 1st for allocation, at December
Board meeting. |